Build a unit rate from scratch

Compose a rate from material, labour, plant, overhead, and margin — and watch each lever move the number.

Every BoQ rate is built, not guessed. Compose one for a Cat6A cabling point from material, labour, plant, overhead, and margin — and watch each lever move the unit rate.
1.5h
12%
20%
MaterialAED 45
Labour (1.5h × AED 35)AED 53
PlantAED 12
Overhead (12%)AED 13
Margin (20%)AED 31
Prime costAED 110
With overheadAED 123
Unit rateAED 153

On a tender with 640 points, this single rate sets a AED 98,112 line — which is why building it from parts beats carrying forward last job's number.